Skip to main content

I-75/I-24 Interchange

Location
Ohio
Market
Federal Government
Services
Architecture / Interior Design / Engineering

The Challenge

In 1934, Building 23 at Wright-Patterson Air Force Base was constructed as an aircraft hangar and test facility. More than 70 years later, the U.S. Air Force wanted to renovate the building to provide a modern lab facility for state-of-the-art energy research. It requested a design that retains the historic feel and aesthetic of the original building, while also creating a modern interior that meets security and force protection requirements.

The Solution

A three-story facility was created within the existing brick shell, adding new spaces for material processing, data acquisition, operations, and fabrication. The design also had special acoustical needs due to the use of vibration-sensitive equipment such as lasers and optical equipment. The superstructure is composed of a structural steel frame and designed to resist collapse in accordance with Antiterrorism/Force Protection (AT/FP) requirements.

Barge Design Solutions provided HVAC, plumbing, steam, lighting and power distribution, communications and security, utilities, storm drainage, lighting protection, and fire protection. Site work included sidewalks, curbs and gutters, access drive control systems, and site upgrades to meet AT/FP requirements. Architectural and interior design were also included as part of the project.

The Impact

The renovation of Building 23 was a testament to Barge's engineering expertise and commitment to excellence. Barge successfully transformed a historic asset into a modern, sustainable, and secure facility, meeting the evolving needs of the U.S. Air Force. The team's ability to balance preservation with innovation while also prioritizing sustainability and security positioned Barge as a valuable partner in this critical project. The project exceeded the original goal of designing to a LEED Silver level, making it the first LEED Gold building on the base.

The Challenge

The proposed TDOT I-75/I-24 Interchange design-build project was one of vast size and scope, featuring multiple bridge and ramp widenings and repairs, 14 new bridges, 21 new retaining walls and a noise wall, lighting, safety and mobility upgrades, and Welcome Center traffic modifications. Created for a densely traveled area, the design-build had to be the most cost-effective, fastest, and safest option for the contractor, owner, and community. During the project's design phase, virtual roadblocks tested Barge Design Solutions with right-of-way challenges, environmental concerns, and an earlier proposed bridge plan that exceeded the budget. It would take innovative solutions to secure the winning bid and move the project forward.

The Solution

The Barge team first addressed the initial TDOT proposed bridge plan at the I-75/I-24 split with a brilliant design flip. By moving the more heavily traveled I-75 roadway to the ground and designing concrete overpasses or new alignments in lieu of steel for new I-24 ramps, the contractor could deliver the project faster and more efficiently, minimizing cost, time, and safety risks.

The second challenge involved right-of-way, where new wider ramps would be built. Purchasing land for the ramps could take months to finalize, so the Barge Design Solutions team proposed to build new ramps right next to the old ones within the existing right-of-way to expedite the process. Barge also proposed that precast MSE retaining walls, a noise wall, and bridge beams be fabricated in an outside controlled setting for high-quality delivery to the site. By using precast elements in the design, it allowed for a reduction in time to the overall construction schedule.

For environmental concerns, eight wetlands had to be moved from the area of construction, requiring permitting and coordination with authorities. Instead of buying credits for rebuilds in the West Tennessee Wetland Mitigation Bank, Barge looked to move the wetlands nearby, finding a location directly outside the site's boundary.

The Result

Finishing the I-75/I-24 Interchange project ahead of schedule, Barge's experience and innovative planning maximized space, minimized traffic disruption for improved safety and timelines, and revised the number of proposed bridges from 14 to 12, reducing the budget. Wetlands and endangered plant species were preserved with minimized costs. And nearby resident requests were met with reduced road noise and improved aesthetics.

Engineering
Transportation
No items found.
I-75/I-24 Interchange
Consult with an Expert
Thank you!
Your message has been submitted
Oops! Something went wrong while submitting the form.

We're collaborative by design. Let's team up.

Begin your project development journey today by contacting us.